Annual Report 2010 by the National Preventive Mechanism against Torture
past twenty years according to a standard building model, designed to
accommodate a large number of inmates (just these four prisons house
approximately 6,000 inmates), which involve a complex with a land area of more
than 7 hectares. Most of the other prisons were built in the 1980s and the oldest
establishments are Martutene (Gipuzkoa), dating from 1948, and El Dueso
(Cantabria), from 1907.
The inside layout of the
323. Regarding the interior layout of the prisons visited, the “standard models”
prisons differs greatly. The
have a wide range of separate interior units, which ensures a more acceptable
standard models have a
wide range of modules and
buildings, allowing a more
satisfactory distribution of
inmates
distribution of inmates (around 14 ordinary residential models, a block for
receptions, departures and transfers, a healthcare building, an solitary
confinement facility, a communications building, a sports centre, a socio
cultural area, kitchen, laundry, workshops and storerooms). The structure of
the other prisons corresponds to very different eras, being highly diverse and
difficult to define systematically. The Alicante-Cumplimiento prison, for
example, is very little suited to custodial purposes given the numerous areas
with reduced visibility, which may hinder appropriate surveillance by the
guards and the inmates’ safety.
Most of the prisons visited
324. Although the current economic crisis has meant a sharp reduction in
are in an acceptable state
prison budgets and, therefore, in the funds available for repair work, the overall
of repair and maintenance.
There are still, however,
certain specific
shortcomings
state of the upkeep and maintenance of most of the establishments visited is
satisfactory, albeit there are still specific and ongoing shortcomings, such as the
unpleasant effects of the power generating units at Madrid II in Alcalá de
Henares (Madrid), the damp patches in the arts and crafts workshops at
Monterroso (Lugo), the cracks in the façade at Pereiro de Aguiar (Ourense), or
the problems of damp in the infirmary at Soria. At the prison in Nanclares de la
Oca (Alava), the scheduled building of a new prison has put a stop to several
planned instances of maintenance and repair work, with the exception of those
deemed essential.
Staff quarters are
As regards the state of repair of the staff quarters, it can be considered acceptable
acceptable in the modern
in the modern prisons, but not so in the older ones, such as Madrid II in Alcalá de
prisons
Henares, Martutene (Gipuzkoa) or Nanclares de la Oca (Alava).
Generally speaking, there is
325. Bearing in mind that, as noted earlier, most second-degree inmates have to
insufficient space and
share a cell, the space and furnishings provided are generally insufficient to cater
furnishing in second
degree cells
for the needs of the inmates occupying them. Furthermore, there is a problem, as
the bunks, which have up to three tiers, tend not to have any guardrails to protect
against falls, which in certain cases have involved serious injuries, as noted during
At the older prisons,
the locking and unlocking
138
some of the inspection visits.
of the cells is not
326. At the more modern establishments, the cells have central locking and
centralised
unlocking, but this is not the case at the older ones. Some of the spy holes in the
THE OMBUDSMAN OF SPAIN
Select target paragraph3
Connect to a paragraph
Connect to an entity
Disable highlights
Add to table of contents