irrespective of statutory requirements – it intended to issue a decree
applying the Technical Guidelines for Fire Prevention 160 N by analogy
or to establish uniform minimum fire protection standards in police
detention centres in some other suitable way.
standards
As of the editorial deadline, no response had yet been received from
the Federal Ministry of the Interior.
The Federal Ministry of the Interior should issue uniform requirements for fire protection
systems in police detention centres nationwide and adapt the level of fire protection to at
least meet the standards applicable to correctional institutions.
2.6.3.
Individual cases
2.6.3.1.
Lack of electrical sockets at the Villach police detention centre
The NPM also brought up the lack of electrical connections or electrical
sockets in the inmate cells at the Villach police detention centre (with
the exception of the two cells for the maintenance workers). The NPM
asked the Federal Ministry of the Interior whether and, if so, when the
Ministry would order the installation of electrical connections in the
inmate cells at the Villach police detention centre for the purpose of
improving occupational opportunities.
Electrical connections in
inmate cells
The Federal Ministry of the Interior replied that three inmate cells in the
Villach police detention centre are equipped with an electrical socket.
In addition, the Ministry is endeavouring to equip inmate cells with
electrical connections within budgetary limits in the course of its
adaptation and renovation work, based on the human rights
standards developed jointly with the NPM.
In discussing occupational opportunities at police detention centres
with the Federal Ministry of the Interior, the NPM emphasised that the
members of the working group jointly established the equipping of
each cell with an electrical socket, which can be switched on or off
from the outside, as a minimum standard.
Thus far, the NPM is not in agreement that this (and other) standards
should only be implemented in the course of “adaptations and
renovations” or within “budgetary limits”. Therefore, the NPM again
asked the Federal Ministry of the Interior when it could order the
installation of electrical connections in the inmate cells at the Villach
police detention centre. Once again the Ministry has not made any
definitive statements in this regard.
Each of the inmate cells at the Villach police detention centre must be equipped with electrical
sockets, which can be switched from the outside (with distributor sockets, if appropriate).